Hitachi Energy and the federal and Ontario governments have announced a $479-million plan to build a new transformer insulation factory to help meet skyrocketing demand from data centres, green energy and industrial development.
“All those investments are creating more demand for components, and transformers are a major element in the customer energy chain,” Bruno Melles, chief executive of Hitachi’s transformers business unit, said in an interview ahead of Friday’s announcement in London, Ont.
“Because in every place where there is power generation and in every place where there is a connection, there is a transformer.”
The 21,000-square-metre facility would be the first in Canada to produce pressboard — a material made from paper pulp that’s key to keeping transformers cool — and the first Hitachi would establish in the Americas. Currently in Canada that material sourced from Europe, Melles said.
Construction is set to be complete by the end of 2028 and the project is expected to create 100 permanent skilled jobs.
Hitachi is shouldering the bulk of the investment, with the federal and Ontario governments collectively contributing $50 million.
Of that, $20 million is through the federal strategic response fund, $10 million is from Natural Resources Canada and up to $20 million is through the Invest Ontario Fund.
Get breaking National news
The power industry has been dealing with supply chain challenges as electricity demand booms. The factory aims to ease at least one of the big pinch points.
“Today we are in a situation where the industry for transformer manufacturing is going at a very high speed, but not all the industrial parts are going at the same speed,” Melles, who is based in Zurich, said.
“This is why we want to give a strong message to the market and say, ‘We want to be an integral part of the supply chain resilience and we are going to invest in order to ensure that the market is not going to have any shortage.'”
In May, Prime Minister Mark Carney announced Canada’s new electricity strategy, which aims to double the country’s electricity grid by 2050.
“Electricity demand in Canada is growing at an unprecedented pace, something we’ve never seen before,” said Carla Vicente, managing director of Hitachi Energy’s Canadian division, in an interview.
“By ensuring that we have this factory operational by the end of 2028, we will be able to respond to the higher needs and demand for the transformers that are an essential part of anything that we want to do to be able to electrify.”
- ‘Local Governance 101’ Okanagan community’s first-ever council trains ahead of inaugural meeting
- Family of soldier badly burned at CFB Wainwright speaks about his injuries
- As B.C. scraps time change, experts have a warning about the risks
- B.C. soldier burned in CFB Wainwright fire remains in Edmonton ICU
Building new infrastructure has been a key focus for Carney’s government, and several power and transmission projects have been referred to the major projects office for a streamlined review.
“By investing in the critical infrastructure needed to power our future, we are supporting economic growth, creating good-paying jobs and strengthening Canada’s economic security,” Industry Minister Mélanie Joly said in a news release.
Vic Fedeli, Ontario’s minister for economic development, job creation and trade, said in a news release that the Hitachi investment will help position the province as a central hub for advanced manufacturing projects.
“In the face of global economic uncertainty, our government continues to foster the competitive conditions needed for global companies to confidently expand their presence in Ontario and invest in long-term projects.”
Melles said the site for the new factory in London was not chosen “as a coincidence.”
He said it will be a good fit with another operation Hitachi has in the southwestern Ontario city. In June, it announced the acquisition of Canduct, a manufacturer of insulation kits and components.
“To have a location that is very, very close to Canduct will allow a simplification of the supply in the value chain, a dramatic reduction of the risks connected to logistics, and then of course we can count on having access to fresh and clean water that is an integral element for the production of insulation material.”
People do not understand the importance of transformers. As of now they come from china. And take years to make. If for example a solar storm knocked out major transformers, large areas could be years with out power. This is helping make canada an independent country.
The only time they pick up a shovel… For a picture..✌️✌️🐸🐸🐸✌️✌️🐸
Disgusting.
Ooh delightful! Vibrators for everyone!!!
Are they going to make the vibrators there? If so, 470 odd million dollars won’t be enough, liberals all want one jammed up their ass and one in each ear. Make the factory bigger.
Lots of negative trolls on today. Lol
This cringe photo reminds me of USSR. “Great success of our motherland”.
All those companies that the government subsidy to come here and at the end, they end up leaving after few years. Instead of helping transnationals, use that tax money to help medium size Canadian owned companies
These elegant people came to dig the soil, but they failed to dress for SAFETY. Regardless of your position in an org, you must dress for the type of job you do at that moment. Otherwise, it’s all about frolicsome comedy.
Meanwhile, pulp mills across the country are all shutting down.
Thanks Mark.
Alberta out!!!
479 million investment to create 100 jobs? Most of that money is clearly going to pay bribes