Monday marks the first day that traffic can officially begin using the city’s newly constructed Waverley Underpass.
The project began in January 2017 and finished sooner than its projected completion date of December 2019.
The construction of the underpass comes after Winnipeg officials say the southwest side of the city has quickly grown, seeing increased traffic due to train operations.
The city says about 30,000 vehicles and between 35 and 40 trains pass through the intersection daily, which has caused the Waverley rail crossing to become a congested area.
Get breaking National news
The construction saw the railway crossing replaced with an underpass at Waverley Street and Taylor Avenue and also prompted the reconstruction of Waverley Street.
- Alberta on track to see the most traffic deaths in a decade: ‘Disaster waiting to happen’
- ‘E-dirt bikes are not toys’: E.R. doc fears more injuries after 2 kids hit in Edmonton
- Woman taken to hospital after Toronto crash involving cyclist and driver
- Surface Green Line LRT route in downtown Calgary endorsed by city committee
Taylor Avenue was also expanded to four lanes between Waverley and Lindsay streets.
Minor landscaping work is expected to take place into 2020.